TSP Name: Northern Border Pipeline Company TSP: 021632583
Notice Type: OFO Critical: Y
Posted Date/Time: 8/7/2017 12:19:47 PM
Notice Eff Date/Time: 8/7/2017 12:19:47 PM Notice End Date/Time: 8/12/2017 9:00:00 AM
Notice Identifier: 1698 Notice Stat Desc: Initiate
Prior Notice:
Reqrd Rsp Desc: No response required Response Date/Time:
 
Notice Text:



Northern Border OFO Watch (Posted 8/7/2017)

Effective immediately Northern Border Pipeline is issuing an OFO watch for its Manning Interconnection (DRN# 378214) and Glen Ullin Interconnection (DRN# 43726), due to cumulative operational imbalance issues. The issuance is per Northern Border Tariff Section 6.10.6 Interruption of Service.

The OFO watch is in effect through gas day August 11, in order to allow the interconnecting party to remediate the cumulative operational imbalance issue. If the interconnect operator is unable to remediate the issue within the given timeframe, Northern Border will, pursuant to Northern Border Tariff Section 6.10.6 Interruption of Service, issue an OFO requiring curtailment of interruptible services and/or forced balancing of nominations and actual flows at these interconnects.

This posting will be updated as more information becomes available.

Please contact your Northern Border Nominations Representative with any questions regarding nominations or scheduling at (888) 750-6275.

Please contact System Operations with any questions regarding operations or facilities.
Paul Oliver 832-320-5885
Monica Edwards 832-320-5822